Notice to Resume Work or of Measures Satisfied – Trans-Northern Pipeline Inc. (TNPI) – Order MP-001-2019 Measure #3

NOTICE TO RESUME WORK OR OF MEASURES SATISFIED
IN THE MATTER OF THE CANADIAN ENERGY REGULATOR ACT,
FOLLOWING AN ORDER UNDER SECTION 109(1)

The undersigned Canada Energy Regulator Inspection Officer hereby notifies:

Information not available

Trans-Northern Pipeline Inc. (TNPI) that the hazardous or detrimental situation described in Order No. MP-001-2019 Measure #3 has been remedied to the satisfaction of the Inspection Officer.

Therefore,

  •       suspended work may resume, and/or
  •  X  the measures specified in the order have been satisfied.
Inspection Officer
Inspection Officer Information not available Information not available Information not available
Name IO Designation # Telephone
6 November 2019 Information not available
_______________________________
Signature
Date
210-517 10 Ave SW, Calgary AB  T2R 0A8

CVA or Incident #: CV1920-222

Date modified: